Aerospace Quality Engineering & APQP Consulting(805) 501-1013Customersupport@airoque.com

AiroQue / Services / Example Control Plans

Examples

Two Control Plans that look nothing alike

Both are Control Plans. One controls a manufacturing process step by step; the other controls a part that passes through the building without being manufactured in it. The format follows the job, not a house template.

About these examples

These are illustrative documents prepared by AiroQue to show structure, depth and tone. All part numbers, drawing numbers, customer and site names, tool and fixture identifiers, internal specification and procedure numbers, and nonconformance reference numbers have been removed or replaced with bracketed placeholders. Process values are representative and are not taken from any released document. Nothing on this page identifies a customer, a program or a part.

A Production process control

Example A — process Control Plan for an assembled, bonded and tested product

Operation-by-operation control of a manufacturing process, with product and process characteristics separated, key characteristics flagged, and a specific reaction written for every row.

Control Plan numberCP-EXAMPLE-A-R03
Part numberEXAMPLE-100-XX
Part nameCable / connector assembly (example)
Drawing numberEXAMPLE-100-XX
Drawing revision[REV] — operations sequenced per current work instruction
Date original[DATE]
Date revised[DATE]
Prepared by[PREPARED BY]
Approved by[QUALITY / ME / PROGRAM]

Twelve representative operations shown. Scroll the table horizontally to see all twelve columns.

Example A — process Control Plan (illustrative)
OpProcess stepMachine / device / jig / toolsCellProduct characteristic (KPO)Process characteristic (KPI)RequirementEvaluation / measurement techniqueSample sizeFrequencyControl methodReaction plan
1Stage work order — verify work order, drawing and current work instruction at the stationWork order, current work instruction, travelerCELL-1 StagingCorrect documentation and configuration at the stationCurrent-revision instruction present; work order matches partWork order, drawing and instruction all at current revisionReview work order and instruction; confirm revision against document control100%Each work orderInitial on traveler before work beginsStop. Do not begin work. Obtain current revision from document control; notify supervisor; confirm no work was performed to a superseded revision.
10Issue parts — issue all required parts per kit list with traceabilityKit list, pick list, ERP systemCELL-1 StagingCorrect parts issued with full traceabilityAll parts issued per kit list; lot traceability recordedCorrect parts and quantities; traceability recorded per procedureVerify physical parts against kit list; confirm lot and batch records100%Each work orderERP transaction and pick list complete before release to assemblyStop. Quarantine kit. Reconcile against kit list, correct the issuance and record the discrepancy per the nonconformance procedure.
20Marking — mark component per drawing noteMarking equipment, marking fixture [FIXTURE ID]CELL-2 AssemblyMarking content, location and legibilityMarking applied with correct fixture setupContent, location and depth per drawingVisual verification against drawing, with magnification where required100%Each assemblyPost-marking verification of content and location before next operationStop. Segregate the unit and do not proceed. Evaluate for rework per procedure; verify fixture setup and re-verify the next three units.
30Cut and strip cable to lengthApproved cutting tool, calibrated strippers, measuring toolCELL-2 AssemblyCut length; strip length; strand integrityTool set to correct length; no nicked or broken strandsLengths per drawing; no strand damage permittedMeasure length; inspect stripped ends under magnification100%Each assemblyLength measurement and strand inspection recordedStop. Scrap the affected piece — rework not permitted. Re-set the tool and verify the next three pieces before resuming.
40Contact assembly — crimp contact to conductorCalibrated crimp tool [TOOL ID], go/no-go gaugeCELL-2 AssemblyCrimp quality and retention (KPC)Correct tool and die; crimp within specificationPer applicable crimp specificationVisual crimp inspection; pull test per specification100% visual; pull test per specificationEach assembly; pull test each lotCrimp inspection and pull-test results recorded against serialStop production. Quarantine every unit produced since the last passing pull test. Verify tool calibration and die; disposition affected units; raise a nonconformance.
50Mix casting compoundCalibrated scale, two-part compoundCELL-2 AssemblyMix ratio, material identity and pot lifeRatio and mix time per manufacturer's data sheet; material within shelf lifeRatio, mix time and cure per manufacturer's data sheetVerify lot and expiry; weigh on calibrated scale; record batch100%Each mixBatch record capturing lot, expiry, ratio and mix timeDiscard the mix. Quarantine any unit assembled with suspect material. Verify scale calibration, re-mix and record.
60Assemble connector bodies to cableCalibrated torque wrench, assembly fixtureCELL-2 AssemblyAssembly sequence, orientation and torqueTorque applied with calibrated wrench in specified sequenceTorque value and sequence per drawingVerify sequence and orientation; apply and record torque100%Each assemblyTorque value recorded against assembly serial numberStop. Segregate the unit. Verify wrench calibration, evaluate the joint for damage and disposition per the nonconformance procedure.
70Verify pin depthCalibrated pin depth gaugeCELL-3 InspectionPin depth (KPC)Gauge within calibration; part seated correctly for measurementDepth within drawing toleranceMeasure with calibrated gauge and record the actual value100%Each assemblyActual reading recorded; KPC results retained per contractStop. Quarantine the unit and all units since the last conforming reading. Notify quality engineering, raise a nonconformance and notify the customer where the contract requires it.
90Cure assemblyCalibrated oven with recording thermocoupleCELL-2 AssemblyCure temperature and durationSet point verified; recorder trace continuous for the full cycleTemperature and time per applicable process specificationVerify set point; monitor recorder trace; retain chart with the batch record100% of batchesEach batchRecorder trace retained with the batch recordStop. Quarantine the batch. Evaluate the excursion against the specification; disposition by engineering; do not release without evaluation.
120Electrical and leak verificationCalibrated dielectric tester, insulation resistance tester, low-resistance ohmmeter, leak test fixtureCELL-3 InspectionDielectric withstand, insulation resistance, conductor resistance, leakage (KPC)Test equipment within calibration; values applied per specificationTest values and limits per applicable test specificationPerform each test at the specified value and record the result100%Each assemblyTest results recorded against serial number and retainedStop. Quarantine the unit; do not retest without engineering approval. Raise a nonconformance and contain units tested since the last calibration verification.
140Final visual inspectionMagnification and controlled lightingCELL-3 InspectionWorkmanship, marking legibility, cleanliness and FODInspection performed under specified lighting and magnificationNo damage, contamination or illegible marking; per workmanship standardVisual inspection against the workmanship standard100%Each assemblyInspection stamp and record applied before release to stockStop. Segregate the unit, disposition per the nonconformance procedure and assess whether the condition affects the remainder of the lot.
150Route to storesCompleted documentation packageCELL-1 StagingDocumentation complete; quantity reconciledAll records present, legible and signedComplete documentation package per procedureFinal review of traveler, inspection records and test records100%Each lotDocumentation package verified before stock receiptHold the lot in quarantine until documentation is complete. Do not receive into stock with missing or illegible records.

What this format is for

Parts manufactured in-house where risk lives in the process: tool settings, cure cycles, crimp quality, torque, test values. The plan follows the routing so it can be read alongside the traveller.

Why the reaction column is long

Each reaction names stop authority, containment boundary, disposition path and what has to be verified before restart. That is what makes the difference between a nonconformance and an escape.

Tailoring applied here

Product and process characteristics in separate columns, cell identification included, key characteristics flagged in the characteristic text, and sample size and frequency split — all because that is what this reviewer expects.

B Pass-through part control

Example B — pass-through part quality Control Plan

For product received, stocked and shipped without internal manufacturing. There are no operations to control, so the plan is organized by known failure condition and by inspection point — receiving, source, stock and shipping.

Control Plan numberCP-EXAMPLE-B-R01
Part numberEXAMPLE-200-01
DescriptionHeat exchanger assembly (example)
Drawing revision[REV]
Part typePass-through — no internal manufacturing operations
Read-across part numbersEXAMPLE-200-02, EXAMPLE-200-03
Primary inspection pointsReceiving, source inspection, stock, shipping
Prepared by[PREPARED BY]
Approved by[QUALITY / ME / PROGRAM]

Twelve representative conditions shown. Scroll horizontally for the full set of columns.

Example B — pass-through quality Control Plan (illustrative)
RefFailure mode / nonconformanceRequirementInspection point(s)Immediate actionContainmentEscalation / notificationRead-across impactPrevention / future checksStatus
QA-01Incorrect or missing port plugsBoth ports plugged with the specified plug type per drawing noteReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock.Quarantine the affected lot. 100% inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — verify plug type and presenceAdd plug type and presence verification to receiving and shipping checklistsOpen
QA-02Incorrect fastener hardware installedHardware type per drawing; only the fasteners identified on the drawing receive the alternate hardwareReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock.Quarantine the affected lot. 100% inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — verify correct hardware at each locationUpdate receiving and shipping checklists with a hardware verification stepOpen
QA-03Bent or non-flush nut platesNut plates flush to the housing with no deformation, per drawingReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock. Do not install.Quarantine the affected lot. 100% visually inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — inspect nut plate conditionAdd a nut plate condition check to the incoming inspection instructionOpen
QA-04Missing protective plugs in test portsProtective plugs installed in all test ports per drawing noteReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock. Install correct plugs only under an approved disposition.Quarantine the affected lot. 100% inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — verify protective plugs presentAdd a port protection verification step at receiving and prior to shipmentOpen
QA-05Missing fire shieldFire shield installed per drawing — safety-related featureReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock. Do not install.Quarantine the affected lot. 100% inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream. Treat as safety-related.All read-across part numbers — verify fire shield presence and attachmentAdd mandatory presence and attachment verification at receipt and shipmentOpen
QA-06Damaged fastener heads or fitting flatsNo visual damage permitted on fastener heads or fitting flatsReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock.Quarantine the affected lot. 100% visually inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — inspect exposed hardwareAdd a visual inspection of all exposed fasteners and fittings to the receiving instructionOpen
QA-07Incomplete or illegible markingAll marking content, location and legibility per the drawing marking noteReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock.Quarantine the affected lot. 100% inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — verify complete and legible markingAdd verification of marking content and legibility to the incoming inspection instructionOpen
QA-08Missing fluid-type identification tagIdentification tag attached per the drawing and packaging requirementReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock.Quarantine the affected lot. 100% inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — verify tag present and correctAdd tag verification to the receiving and shipping checklistsOpen
QA-09Coating touch-up exceeds the allowable areaTouch-up limited to the area permitted by the applicable coating specificationReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock.Quarantine the affected lot. 100% visually inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — assess coating conditionAdd a visual assessment of touch-up extent against the specification limitOpen
QA-10Uninstalled components not boxed and attachedUninstalled components boxed and attached to the unit per the packaging requirementReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock. Locate the loose components before any movement.Quarantine the affected lot. 100% inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — verify component presence and attachmentSource inspection to verify presence and attachment before releaseOpen
QA-11Specified feature not counterbored or countersunkCounterbore/countersink present where specified on the drawingReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock. Do not install.Quarantine the affected lot. 100% dimensionally inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream.All read-across part numbers — verify the specified featureAdd dimensional verification of the specified feature at receiptOpen
QA-12FOD found in air passagesAll parts free of foreign object debris per the applicable FOD control requirementReceiving, source, stock, shippingStop. Quarantine the unit; do not ship, install or move to stock. Do not blow out or clean before evaluation.Quarantine the affected lot. 100% inspect stock and in-transit units for the same condition.Notify lead/supervisor and quality engineering. Escalate to the supplier where the condition originates upstream. Treat as safety-related.All read-across part numbers — inspect all passages and openingsAdd FOD inspection of all air passages at receipt and prior to shipmentOpen

Instructions at the inspection point

A plan like this is used by receiving inspectors and material handlers, so the response rules sit on the document itself:

  • Stop immediately on discovering any listed condition. Do not continue processing or ship the unit.
  • Quarantine the affected unit and any units of the same lot in stock or in transit.
  • Document everything: part number, serial or lot, quantity, location, date, and photographs of the condition.
  • Notify the lead or supervisor immediately, and quality engineering for any safety-related condition.
  • Contain: inspect 100% of stock and in-transit units for the same condition before releasing any of them.
  • Notify the supplier where the condition originated upstream, following the purchasing and supplier quality process.
  • Notify the customer where the contract requires notification for the condition or the disposition.
  • Root cause and disposition are determined by quality engineering with manufacturing engineering, not at the inspection point.
  • Update checklists, instructions and training once a condition recurs; this document is maintained as conditions are added or closed.

Why this one is organized by failure mode

When you do not manufacture the part, you cannot control the process that produced it. What you can control is detection at the points the part passes through, and the response when a known condition appears. Read-across is included because these conditions rarely affect only one part number.

Tailoring applied here

Columns for containment, escalation, read-across impact and status, plus a living-document status field — because this plan is maintained as conditions are added and closed, rather than revised only at engineering change.

C The point

The format is a decision, and it is yours

Column structure

Added, removed, merged or renamed to match the form your reviewer expects to receive.

Classification

Special, key and critical designations applied using your customer's symbols and definitions.

Numbering

Operation and characteristic numbering matched to your router, records and drawing balloons.

Wording

Written for engineers, for the floor, or bilingual — using your plant's names for cells, tools and forms.

Want to see this against your own part?

Send a drawing and a routing under NDA. AiroQue can produce a short sample section of a Control Plan in your customer's format before you commit to the full document.